40 CFR 60.5380c
§ 60.5380c What if I do not meet the final control plan increment of progress compliance date?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 60.5380c, § 60.5380c What if I do not meet the final control plan increment of progress compliance date?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/173259
- Permanent ID
ys:prov:173259@1- SHA-256
0ff66afe055e0742cb4c9bd40e7195b403bd1de142626e08b6d7e6169e8d6f1f
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
If you fail to meet the final compliance control plan increment of progress report compliance date, you must submit a notification to the Administrator postmarked within 10 business days after the required submittal date for that increment of progress. You must inform the Administrator that you did not meet the increment, and you must continue to submit reports each subsequent calendar month until the increment of progress is met.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.