40 CFR 60.5845b
§ 60.5845b What affected EGUs must I address in my State plan?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 60.5845b, § 60.5845b What affected EGUs must I address in my State plan?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/173363
- Permanent ID
ys:prov:173363@1- SHA-256
8babd009424ecb7113acc2d213c7996eb127d457421dbfd043112551337a2e4c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The EGUs that must be addressed by your State plan are:
(1) Any affected EGUs that were in operation or had commenced construction on or before January 8, 2014;
(2) Coal-fired steam generating units that commenced a modification on or before May 23, 2023.
(b) An affected EGU is a steam generating unit that meets the relevant applicability conditions specified in paragraphs (b)(1) through (2) of this section, as applicable, except as provided in § 60.5850b.
(1) Serves a generator capable of selling greater than 25 MW to a utility power distribution system; and
(2) Has a base load rating (i.e., design heat input capacity) greater than 260 GJ/hr (250 MMBtu/hr) heat input of fossil fuel (either alone or in combination with any other fuel).
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.