§ 60.6060 What must I include in my notice of construction?

United States · 40 CFR — Protection of Environment · Status: effective

Get this as JSONEmbed this
Cite this
Citation
40 CFR 60.6060, § 60.6060 What must I include in my notice of construction?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/173448
Permanent ID
ys:prov:173448@1
SHA-256
1aaf8a2ac373396a6b9753fc010baf8eece817cc346bd673b8161ed6d1bfe5d0

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Include all the following ten items: (1) A statement of your intent to construct the municipal waste combustor. (2) The planned initial startup date of your municipal waste combustor. (3) The types of fuels you plan to combust in your municipal waste combustor. (4) The capacity of your municipal waste combustor including supporting capacity calculations, as specified in § 60.6015. (5) Your siting analysis, as specified in § 60.5805. (6) Your final materials separation plan, as specified in § 60.5785. (7) Your notice of the second public meeting (siting analysis meeting), as specified in § 60.5810(b). (8) A transcript of the second public meeting, as specified in § 60.5820(d). (9) A copy of the document that summarizes your responses to the public comments you received during the second public comment period, as specified in § 60.5825(a). (10) Your final siting analysis, as specified in § 60.5825(c). (b) Submit your notice of construction no later than 30 days after you commence construction, reconstruction, or modification of your municipal waste combustor.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.