yourstate.us
40 CFR 60.6075

§ 60.6075 When must I submit the initial performance test report?

United States · 40 CFR — Protection of Environment · Status: effective

Get this as JSONEmbed this
Cite this
Citation
40 CFR 60.6075, § 60.6075 When must I submit the initial performance test report?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/173451
Permanent ID
ys:prov:173451@1
SHA-256
02b3acd39fdbc67e86b60b5b3c0ab51a1716f439850aa73004c2d3e91de744a3

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

As specified in § 60.8(a), submit your initial performance test report within 60 days after your municipal waste combustor reaches the maximum load level at which it will operate, but no later than 180 days after its initial startup.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.