40 CFR 60.6570
§ 60.6570 What requirements must I meet for estimating my municipal waste combustor capacity?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 60.6570, § 60.6570 What requirements must I meet for estimating my municipal waste combustor capacity?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/173535
- Permanent ID
ys:prov:173535@1- SHA-256
a9ac3eaee1f94045bf2bbfbfe60d59d04efbad3e5e5c3ef9ee51d95e6076ee38
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) You must calculate the capacity for each continuous municipal waste combustor (e.g., capable of combusting continuously for a 24-hour period) based on 24 hours of operation at the maximum charging rate. You must determine the maximum charging rate separately for combustors that are designed based on heat capacity and for combustors that are not designed based on heat capacity.
(1) For combustors that are designed based on heat capacity, calculate the maximum charging rate based on the maximum design heat input capacity of the unit and a heating value of 12,800 kilojoules per kilogram for combustors firing refuse-derived fuel or a heating value of 10,500 kilojoules per kilogram for combustors firing municipal solid waste that is not refuse-derived fuel.
(2) For combustors that are not designed based on heat capacity, the maximum charging rate is the maximum design charging rate.
(b) You must calculate the capacity for each batch feed municipal waste combustor based on the maximum design amount of municipal solid waste that can be charged per batch multiplied by the maximum number of batches that could be processed in a 24-hour period.
(1) You must calculate the maximum number of batches that could be processed in a 24-hour period by dividing 24 hours by the design number of hours required to process one batch of municipal solid waste. The maximum number of batches may include a fraction (e.g., if one batch requires 16 hours, then 24/16, or 1.5 batches, could be combusted in a 24-hour period).
(2) For batch combustors that are designed based on heat capacity, calculate the municipal waste combustor capacity in megagrams per day, based on the design heating value of 12,800 kilojoules per kilogram for combustors firing refuse-derived fuel, or a heating value of 10,500 kilojoules per kilogram for combustors firing municipal solid waste that is not refuse-derived fuel.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.