40 CFR 62.14670a
§ 62.14670a Is there a minimum amount of monitoring data I must obtain?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 62.14670a, § 62.14670a Is there a minimum amount of monitoring data I must obtain?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/174693
- Permanent ID
ys:prov:174693@1- SHA-256
0bbd4aa4ab22f8f14c2e97d8c09ca3c4b5ae4a950e9057b733e26aa83078c680
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
For each continuous monitoring system required or optionally allowed under § 62.14665a, you must monitor and collect data according to this section:
(a) You must operate the monitoring system and collect data at all required intervals at all times compliance is required except for periods of monitoring system malfunctions or out-of-control periods, repairs associated with monitoring system malfunctions or out-of-control periods (as specified in § 62.14705a(o)), and required monitoring system quality assurance or quality control activities including, as applicable, calibration checks and required zero and span adjustments. A monitoring system malfunction is any sudden, infrequent, not reasonably preventable failure of the monitoring system to provide valid data. Monitoring system failures that are caused in part by poor maintenance or careless operation are not malfunctions. You are required to effect monitoring system repairs in response to monitoring system malfunctions or out-of-control periods and to return the monitoring system to operation as expeditiously as practicable.
(b) You may not use data recorded during monitoring system malfunctions, repairs associated with monitoring system malfunctions or out-of-control periods, or required monitoring system quality assurance or control activities in calculations used to report emissions or operating levels. You must use all the data collected during all other periods, including data normalized for above scale readings, in assessing the operation of the control device and associated control system.
(c) Except for periods of monitoring system malfunctions or out-of-control periods, repairs associated with monitoring system malfunctions or out-of-control periods, and required monitoring system quality assurance or quality control activities including, as applicable, calibration checks and required zero and span adjustments, failure to collect required data is a deviation of the monitoring requirements.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.