40 CFR 62.14695a
§ 62.14695a What information must I submit following my initial performance test?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 62.14695a, § 62.14695a What information must I submit following my initial performance test?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/174698
- Permanent ID
ys:prov:174698@1- SHA-256
ed20c25d4c0597be5aa8a40558a530a7f85afadfd4df9992d410988d43082722
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
You must submit the information specified in paragraphs (a) through (c) of this section no later than 60 days following the initial performance test. All reports must be signed by the facilities manager:
(a) The complete test report for the initial performance test results obtained under § 62.14625a, as applicable;
(b) The values for the site-specific operating limits established in § 62.14605a or § 62.14610a; and
(c) If you are using a fabric filter to comply with the emission limitations in this subpart, documentation that a bag leak detection system has been installed and is being operated, calibrated, and maintained as required by § 62.14665a(b).
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.