40 CFR 63.549
§ 63.549 Notification requirements.
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 63.549, § 63.549 Notification requirements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/175256
- Permanent ID
ys:prov:175256@1- SHA-256
3e5d882165d76c7a5a6889e15d49063c8be4811b235eb3c3f7c9d545c69c3e9c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) You must comply with all of the notification requirements of § 63.9. Electronic notifications are encouraged if suitable for the specific case (e.g., by electronic media such as Excel spreadsheet, on CD or hard copy), and when required by this subpart.
(b) You must submit the fugitive dust control standard operating procedures manual required under § 63.545(a) and the standard operating procedures manual for baghouses required under § 63.548(a) to the Administrator or delegated authority along with a notification that the smelter is seeking review and approval of these plans and procedures. You must submit this notification no later than January 7, 2013. For sources that commenced construction or reconstruction after January 5, 2012, you must submit this notification no later than 180 days before startup of the constructed or reconstructed secondary lead smelter, but no sooner than January 5, 2012. For an affected source that has received a construction permit from the Administrator or delegated authority on or before January 5, 2012, you must submit this notification no later than January 7, 2014.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.