§ 63.1181 How do I comply with the particulate matter standards for existing, new, and reconstructed cupolas?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 63.1181, § 63.1181 How do I comply with the particulate matter standards for existing, new, and reconstructed cupolas?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/175690
- Permanent ID
ys:prov:175690@1- SHA-256
23acac8c7b9a05c3ac7116a7b191cb0b93e62ff2ee998efa4617950a40c939fc
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
To comply with the PM standards, you must meet all of the following:
(a) Install, adjust, maintain, and continuously operate a bag leak detection system for each fabric filter.
(b) Do a performance test as specified in § 63.1188 of this subpart and show compliance with the PM emission limits while the bag leak detection system is installed, operational, and properly adjusted.
(c) Begin corrective actions specified in your operations, maintenance, and monitoring plan required by § 63.1187 of this subpart within one hour after the alarm on a bag leak detection system sounds. Complete the corrective actions in a timely manner.
(d) Develop and implement a written QIP consistent with compliance assurance monitoring requirements of 40 CFR 64.8(b) through (d) when the alarm on a bag leak detection system sounds for more than five percent of the total operating time in a six-month reporting period.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.