40 CFR 63.7783
§ 63.7783 When do I have to comply with this subpart?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 63.7783, § 63.7783 When do I have to comply with this subpart?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/177168
- Permanent ID
ys:prov:177168@1- SHA-256
8b2252de6d457eccc08657aca15d02a37f79d048f6ad9de037af1a161122786d
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) If you have an existing affected source, you must comply with each emission limitation, standard, and operation and maintenance requirement in this subpart that applies to you by the dates specified in paragraphs (a)(1) and (2) of this section. This paragraph does not apply to the emission limitations for BOPF group: mercury (Hg); sinter plant windbox: Hg, hydrochloric acid (HCl), carbonyl sulfide (COS); Blast Furnace casthouse: HCl, total hydrocarbon (THC); Blast Furnace stove: HCl and total hydrocarbon (THC); primary emission control system for a BOPF: 2,3,7,8-tetrachlorodibenzo-p-dioxin (2,3,7,8-TCDD) toxic equivalent (TEQ), HCl, THC; fugitive and intermittent particulate sources.
(1) No later than May 22, 2006 for all emissions sources at an existing affected source except for a sinter cooler at an existing sinter plant.
(2) No later than January 13, 2007 for a sinter cooler at an existing sinter plant.
(b) If you have a new affected source and its initial startup date is on or before May 20, 2003, then you must comply with each emission limitation, standard, and operation and maintenance requirement in this subpart that applies to you by May 20, 2003. This paragraph does not apply to the emission limitations for mercury.
(c) If you have a new affected source and its initial startup date is after May 20, 2003, you must comply with each emission limitation, standard, and operation and maintenance requirement in this subpart that applies to you upon initial startup. This paragraph does not apply to the emission limitations for mercury.
(d) If your integrated iron and steel manufacturing facility is not a major source and becomes a major source of HAP, the following compliance dates apply to you.
(1) Any portion of the existing integrated iron and steel manufacturing facility that becomes a new affected source or a new reconstructed source must be in compliance with this subpart upon startup.
(2) All other parts of the integrated iron and steel manufacturing facility must be in compliance with this subpart no later than 2 years after it becomes a major source.
(e) You must meet the notification and schedule requirements in § 63.7840. Several of these notifications must be submitted before the compliance date for your affected source.
(f) With regard to the mercury emission limitations, if you have a new or existing affected source, you must comply with each emission limitation for mercury that applies to you by the deadlines set forth in § 63.7791.
(g) If you have an affected source for which construction or reconstruction commenced on or before July 31, 2023, each sinter plant windbox, BF casthouse, BF stove, primary emission control system for a BOPF, and fugitive and intermittent particulate source at your facility must be in compliance with the applicable emission limits in table 1 to this subpart through performance testing under § 63.7825 and work practice standards in § 63.7793 by April 3, 2027.
(h) Affected sources that commence construction or reconstruction after July 31, 2023, must be in compliance with provisions in this subpart through performance testing by April 3, 2024 or upon startup, whichever is later.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.