yourstate.us
40 CFR 63.7827

§ 63.7827 How do I demonstrate initial compliance with the operation and maintenance requirements that apply to me?

United States · 40 CFR — Protection of Environment · Status: effective

Get this as JSONEmbed this
Cite this
Citation
40 CFR 63.7827, § 63.7827 How do I demonstrate initial compliance with the operation and maintenance requirements that apply to me?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/177182
Permanent ID
ys:prov:177182@1
SHA-256
609785062bb3dffb93a04e1fc49bb72086a4015a34b982a101319791f3c99b9b

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) For a capture system applied to emissions from a sinter plant discharge end or blast furnace casthouse or to secondary emissions from a BOPF, you have demonstrated initial compliance if you meet all of the conditions in paragraphs (a)(1) through (4) of this section. (1) Prepared the capture system operation and maintenance plan according to the requirements of § 63.7800(b), including monthly inspection procedures and detailed descriptions of the operating parameter(s) selected to monitor the capture system; (2) Certified in your performance test report that the system operated during the test at the operating limits established in your operation and maintenance plan; (3) Submitted a notification of compliance status according to the requirements in § 63.7840(e), including a copy of the capture system operation and maintenance plan and your certification that you will operate the capture system at the values or settings established for the operating limits in that plan; and (4) Prepared a site-specific monitoring plan according to the requirements in § 63.7831(a). (b) For each control device subject to operating limits in § 63.7790(b)(2) or (3), you have demonstrated initial compliance if you meet all the conditions in paragraphs (b)(1) through (3) of this section. (1) Prepared the control device operation and maintenance plan according to the requirements of § 63.7800(b), including a preventative maintenance schedule and, as applicable, detailed descriptions of the corrective action procedures for baghouses and other control devices; (2) Submitted a notification of compliance status according to the requirements in § 63.7840(e), including a copy of the operation and maintenance plan; and (3) Prepared a site-specific monitoring plan according to the requirements in § 63.7831(a).

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.