40 CFR 63.11161
§ 63.11161 What are my compliance dates?
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 63.11161, § 63.11161 What are my compliance dates?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/177802
- Permanent ID
ys:prov:177802@1- SHA-256
22a448ccfa374a19513f55de620f772cfa89c46eec8e3c67f251e20127853548
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) If you have an existing affected source, you must achieve compliance with applicable provisions in this subpart by January 23, 2007. If you startup a new sintering machine at an existing affected source after January 23, 2007, you must achieve compliance with the applicable provisions in this subpart not later than 180 days after startup.
(b) If you have a new affected source, you must achieve compliance with applicable provisions in this subpart according to the dates in paragraphs (b)(1) and (2) of this section.
(1) If you startup a new affected source on or before January 23, 2007, you must achieve compliance with applicable provisions in this subpart not later than January 23, 2007.
(2) If you startup a new affected source after January 23, 2007, you must achieve compliance with applicable provisions in this subpart upon initial startup.