7 CFR 624.9
§ 624.9 Time limits.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 624.9, § 624.9 Time limits, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/19119
- Permanent ID
ys:prov:19119@1- SHA-256
fbe570c9f97550b7edb76b06eabec8f4aa4c6a3c0a00f9083145063965728eeb
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Funds must be obligated by the State Conservationist and construction completed within 220 calendar days after the date funds are committed to the State Conservationist, except for exigency situations in which case the construction must be completed within 10 days after the date the funds are committed.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.