7 CFR 634.19
§ 634.19 Project completion and closeout.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 634.19, § 634.19 Project completion and closeout, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/19237
- Permanent ID
ys:prov:19237@1- SHA-256
984263cd0484058d3d06f0b167f3f8cae03ee4179a06c66317c819ec9a222952
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The maximum total life of a project shall be fifteen (15) years or less.
(b) The allowable contracting period may be increased if an adequate level of participation has been achieved and the designated management agency assures a significant increase in participation can be reached in a reasonable time.
(c) The grant or fund transfer agreement with an administering agency shall expire when the administering agency has fulfilled all of its obligations in the long-term RCWP contracts.
(d) When a project is completed, the administering agency is to provide the State Conservationist, NRCS, a closeout report which summarizes the actions accomplished.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.