yourstate.us
7 CFR 654.11

§ 654.11 Sponsor(s)' responsibility.

United States · 7 CFR — Agriculture · Status: effective

Get this as JSONEmbed this
Cite this
Citation
7 CFR 654.11, § 654.11 Sponsor(s)' responsibility, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/19328
Permanent ID
ys:prov:19328@1
SHA-256
1886829cf294dfedb55f381742bb8cb8adf2418a768c3c53a9e909865be7ede0

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) On non-Federal land, sponsor(s) are responsible for financing and performing without cost to the Federal Government, needed operation and maintenance (O&M) of project measures installed with Federal financial assistance. (b) The Federal agency administering Federal land involving project measures is responsible either for performing or requiring the performance of O&M on land administered by that agency. If project measures benefit both Federal and non-Federal land or interests, the O&M may be performed by the Federal agency, the sponsor(s), or both as mutually agreed by the Federal agency, sponsor(s), and NRCS. If O&M of project measures is performed by mutual agreement, the cost of O&M may be shared by the Federal agency and sponsor(s) as agreed. (c) The sponsor(s) shall obtain NRCS approval before modifying a project measure of changing land use to fulfill a different purpose.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.