yourstate.us
7 CFR 654.17

§ 654.17 Inspection.

United States · 7 CFR — Agriculture · Status: effective

Get this as JSONEmbed this
Cite this
Citation
7 CFR 654.17, § 654.17 Inspection, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/19334
Permanent ID
ys:prov:19334@1
SHA-256
2b1e94e919e96393afa3b3a70f3e2b81932b8aeb30ba0625dbf41234527fdabc

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Sponsor(s) are to make periodic and special inspections of installed project measures as provided in the plan of O&M. For structural measures, inspections are to be made at least annually and after each major storm or occurrence of any unusual condition that might adversely affect the project measures. At the discretion of the State Conservationist, NRCS may assist sponsor(s) with their inspections. NRCS or land-administering agencies may make independent inspections at any time during the period covered by the O&M agreement. (b) Sponsor(s) are to maintain a written record of each inspection and furnish NRCS and land-administering agencies a copy of that record. The record should indentify items inspected, O&M work that may be needed, a time frame to do the work, and the date of the inspection. The NRCS and land-administering agencies will provide the sponsor(s) a copy of a similar record of independent inspections. (c) The sponsor(s) shall perform the O&M work listed as needed in the inspection reports within the time frame established for each item of work. Failure to perform O&M work will be considered a violation of the O&M agreement and will be handled in accordance with § 654.20. (d) Sponsor(s) are to maintain a written record of work performed which is listed in the inspection report and a record of other significant O&M activity. The record will identify the measure, item of work, cost of performance, and date completed. (e) Sponsor(s)' records relative to the project shall be made available to NRCS for examination.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.