7 CFR 654.19
§ 654.19 Plan of operation and maintenance.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 654.19, § 654.19 Plan of operation and maintenance, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/19336
- Permanent ID
ys:prov:19336@1- SHA-256
4189d5c79d8cac1f9c22878749d3a037fc97d3119fdbfabefbe95fbfb3e914fc
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The plan for O&M shall be incorporated into and made a part of the O&M agreement. A separate plan of O&M shall be prepared for each project measure that is expected to a have a unique O&M need. Two or more measures with similar O&M needs may be included in a single plan for O&M.
(b) The plan of O&M shall include the known and anticipated items of O&M, an explanation of how the O&M activities may be carried out, a general time frame for making O&M inspections and for completing the needed O&M work, and the records and reports deemed appropriate by the sponsor(s) and NRCS.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.