40 CFR 1065.395
§ 1065.395 Inertial PM balance verifications.
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 1065.395, § 1065.395 Inertial PM balance verifications, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/195754
- Permanent ID
ys:prov:195754@1- SHA-256
cfe99446fe4ec1edf6b3a6eac4d04c1d0efa237402fdca305196c7a6f7113c3c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
This section describes how to verify the performance of an inertial PM balance.
(a) Independent verification. Have the balance manufacturer (or a representative approved by the balance manufacturer) verify the inertial balance performance within 370 days before testing.
(b) Other verifications. Perform other verifications using good engineering judgment and instrument manufacturer recommendations.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.