§ 50-201.201 Breach of stipulations.

United States · 41 CFR — Public Contracts and Property Management · Status: effective

Get this as JSONEmbed this
Cite this
Citation
41 CFR 50-201.201, § 50-201.201 Breach of stipulations, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/196525
Permanent ID
ys:prov:196525@1
SHA-256
8e555623034fe68e0c49621972385753c96be58b9371fb25220b72282fc679fb

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Whenever the Department of Labor notifies the head of a contracting agency that a contractor is liable for liquidated damages by reason of a breach of stipulations as provided in section 2 of the act, there shall be withheld from any balance due under the contract such amount as may be necessary to satisfy such liability pending final disposition of the case. (b) Whenever a final determination of a breach of stipulations is made, the Secretary of Labor will furnish to the contracting agency a copy of the findings and decision with such recommendations as will assist the contracting agency in determining whether or not the contract should be canceled for such breach.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.