§ 101-5.104-4 Scheduling feasibility studies.
United States · 41 CFR — Public Contracts and Property Management · Status: effective
Cite this
- Citation
- 41 CFR 101-5.104-4, § 101-5.104-4 Scheduling feasibility studies, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/197141
- Permanent ID
ys:prov:197141@1- SHA-256
09a0f1fddb0cd3aa20fdd5d7492cdc5fe630f1d0a9e08c895d26ce904cfdb98a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The schedule of feasibility studies will be coordinated by GSA with its construction, space management, and buildings management programs. Before initiating the study, the Administrator of General Services, or his authorized designee, will give at least 30 days' notice to the head of each agency that would be served by the proposed centralized facility. Such notice will contain an indication of the cost elements involved and the general procedures to be followed in the study.