41 CFR 101-26.102-3
§ 101-26.102-3 Procurement leadtime.
United States · 41 CFR — Public Contracts and Property Management · Status: effective
Cite this
- Citation
- 41 CFR 101-26.102-3, § 101-26.102-3 Procurement leadtime, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/197388
- Permanent ID
ys:prov:197388@1- SHA-256
86b55cd48658750a751bcea8160aa237bebd09869bcc17a99a773133a2423ef8
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
When GSA performs the purchasing services for other agencies or activities as contemplated by this § 101-26.102-3, calculation of the delivery dates required for the items involved must be based on the procurement leadtimes illustrated in the GSA publication, FEDSTRIP Operating Guide. These leadtimes are based on the normal time required after receipt of agency requisitions by GSA to effect delivery to destinations within the 50 States.
(a) Time required to obtain any additional essential information from the requisitioning office for use in issuing a solicitation for bids or offers is not included in the leadtimes.
(b) If unusually large quantities or complex items are required, leadtime adjustments should be made to reflect the specific requirement. As an example, standard furniture items can usually be delivered in less than 90 days after receipt of the requisition. However, for large quantity or complex orders requiring a definite quantity procurement, delivery times may range from 4 to 6 months. Footnotes relating to classes where this is a frequent occurrence are shown in the procurement leadtime table illustrated in the FEDSTRIP Operating Guide.
(c) The procurement leadtime table illustrated in the FEDSTRIP Operating Guide does not apply to public exigency or other high priority requisitions; however, it should be used as a guide to establish realistic required delivery dates for such requisitions.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.