yourstate.us
41 CFR 105-72.702

§ 105-72.702 Enforcement.

United States · 41 CFR — Public Contracts and Property Management · Status: effective

Get this as JSONEmbed this
Cite this
Citation
41 CFR 105-72.702, § 105-72.702 Enforcement, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/199114
Permanent ID
ys:prov:199114@1
SHA-256
171f95de2d45ff7b0bc178de72550ec055fc8ee02867f85f6036e13a2274cd98

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Remedies for noncompliance. If a recipient materially fails to comply with the terms and conditions of an award, whether stated in a Federal statute, regulation, assurance, application, or notice of award, the Federal awarding agency may, in addition to imposing any of the special conditions outlined in § 105-72.204, take one or more of the following actions, as appropriate in the circumstances. (1) Temporarily withhold cash payments pending correction of the deficiency by the recipient or more severe enforcement action by the Federal awarding agency. (2) Disallow (that is, deny both use of funds and any applicable matching credit for) all or part of the cost of the activity or action not in compliance. (3) Wholly or partly suspend or terminate the current award. (4) Withhold further awards for the project or program. (5) Take other remedies that may be legally available. (b) Hearings and appeals. In taking an enforcement action, the awarding agency shall provide the recipient an opportunity for hearing, appeal, or other administrative proceeding to which the recipient is entitled under any statute or regulation applicable to the action involved. (c) Effects of suspension and termination. Costs of a recipient resulting from obligations incurred by the recipient during a suspension or after termination of an award are not allowable unless the awarding agency expressly authorizes them in the notice of suspension or termination or subsequently. Other recipient costs during suspension or after termination which are necessary and not reasonably avoidable are allowable if paragraph (c) (1) and (2) of this section apply. (1) The costs result from obligations which were properly incurred by the recipient before the effective date of suspension or termination, are not in anticipation of it, and in the case of a termination, are noncancellable. (2) The costs would be allowable if the award were not suspended or expired normally at the end of the funding period in which the termination takes effect. (d) Relationship to debarment and suspension. The enforcement remedies identified in this section, including suspension and termination, do not preclude a recipient from being subject to debarment and suspension under E.O.s 12549 and 12689 and the Federal awarding agency implementing regulations (see § 105-72.203).

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.