41 CFR 109-28.5004
§ 109-28.5004 Justification and review procedures.
United States · 41 CFR — Public Contracts and Property Management · Status: effective
Cite this
- Citation
- 41 CFR 109-28.5004, § 109-28.5004 Justification and review procedures, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/199273
- Permanent ID
ys:prov:199273@1- SHA-256
f30eef16b92a372698efdd4c399be231cf41e42af29a0cf98c4e8a55fc9278eb
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Procedures shall provide for the following:
(a) The original decision to classify and retain equipment as EHFFP shall be justified in writing, providing sufficient detail to support the need for retention of the equipment. This justification will cite the project for which retained, the potential use to be made of the equipment, or other reasons for retention.
(b) The validity of the initial classification EHFFP shall be reviewed by management at a level above that of the individual making the initial determination.
(c) Retention of equipment as EHFFP must be rejustified annually to ensure that original justifications remain valid. The rejustifications will contain sufficient detail to support retention.
(d) When equipment is retained as EHFFP for longer than one year, the annual rejustification shall be reviewed at a level of management at least two levels above that of the individual making the determination to retain the EHFFP. Equipment retained as EHFFP for longer than three years should be approved by the head of the DOE field organization.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.