yourstate.us
Nev. Rev. Stat. § 11.2055

Actions for damages for injury or wrongful death caused by deficiency in construction of improvements to real property: Determination of date of substantial completion of improvement to real property

Nevada · Nevada Revised Statutes Chapter 11 — Limitation of Actions · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Nev. Rev. Stat. § 11.2055, Actions for damages for injury or wrongful death caused by deficiency in construction of improvements to real property: Determination of date of substantial completion of improvement to real property, Nevada, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2071410
Permanent ID
ys:prov:2071410@1
SHA-256
bb046586dc9994a74d9899271deb8d31bc44bf018a8bd335c073a552a79dfb13

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

1. Except as otherwise provided in subsection 2, for the purposes of this section and NRS 11.202, the date of substantial completion of an improvement to real property shall be deemed to be the date on which: (a) The final building inspection of the improvement is conducted; (b) A notice of completion is issued for the improvement; or (c) A certificate of occupancy is issued for the improvement, Ê whichever occurs later. 2. If none of the events described in subsection 1 occurs, the date of substantial completion of an improvement to real property must be determined by the rules of the common law.