Nev. Rev. Stat. § 108.231

Notice of lien against two or more separate buildings or mining claims: Designation of amount due on each; effect of failure to designate amount due on each

Nevada · Nevada Revised Statutes Chapter 108 — Statutory Liens · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Nev. Rev. Stat. § 108.231, Notice of lien against two or more separate buildings or mining claims: Designation of amount due on each; effect of failure to designate amount due on each, Nevada, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2080291
Permanent ID
ys:prov:2080291@1
SHA-256
63155c9e1549f8ab2a4b5d9334b4e013793b5fdd992157bb46a1ddd600458c8a

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

1. In every case in which a notice of lien is recorded against two or more separate buildings or mining claims that are owned by the same person and that are located on separate legal parcels that existed at the commencement of construction, the lien claimant must, at the time of recording the notice of lien, designate the lienable amount due on each building or mining claim. 2. The lien of a lien claimant only applies to the lienable amount designated in the notice of lien, plus all amounts that may be awarded by the court pursuant to NRS 108.237, as against other creditors having liens by judgment or otherwise, upon the buildings or mining claims. However, the lienable amount chargeable to the interest of the owner in each building must be the total amount of the lien claimant’s notice of lien, without regard to the proportionate amount designated to each separate building in the lien claimant’s notice of lien, plus all amounts that may be awarded by the court pursuant to NRS 108.237, but upon the trial thereof, the court may, where it deems it equitable to do so, distribute the lien equitably as among the several buildings involved. 3. If a lien claimant fails to designate in the notice of lien the amount due on each separate building as provided in subsection 1, the lien claimant’s notice of lien must be postponed to the notices of lien of other lien claimants and other encumbrancers for value who have designated the amount due on each building or mining claim but must not be inferior to any rights or interests of the owner. For purposes of this subsection, a lien claimant’s lien must not be postponed to other liens or encumbrances if the lien claimant’s designation among the parcels was estimated by the lien claimant in good faith or was based upon a pro rata division of the total lienable amount.