43 CFR 404.8

§ 404.8 Are there any exceptions that would allow a community with greater than 50,000 inhabitants to be part of an eligible rural water supply project?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 404.8, § 404.8 Are there any exceptions that would allow a community with greater than 50,000 inhabitants to be part of an eligible rural water supply project?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/210244
Permanent ID
ys:prov:210244@1
SHA-256
9724634f93637ec60c733dabc974e50ab7d3e8578e562a9995146f618cb2ec1b

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Yes. A town or community with a population in excess of 50,000 inhabitants may participate in or be served by an eligible rural water supply project under this program if Reclamation determines that the town or community is a critical partner whose involvement substantially contributes to the financial viability of the proposed project. Such a community could be expected to bear a greater proportionate share of the planning, design, and construction costs than other project sponsors, consistent with their capability to pay and the benefits they derive from the project.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.