43 CFR 404.48
§ 404.48 What process will Reclamation follow to determine if a feasibility study is ready for review?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 404.48, § 404.48 What process will Reclamation follow to determine if a feasibility study is ready for review?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/210287
- Permanent ID
ys:prov:210287@1- SHA-256
2e609b82a838d86924aa8312522dfd1827617ca833c0648a1db629a51fe8e433
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Reclamation will evaluate whether the feasibility study adequately addresses all of the items required in Reclamation's standards for conducting a feasibility study, and is, therefore, ready for review. Reclamation standards and requirements for the content of a feasibility study are available at your local Reclamation office. Reclamation will notify you in writing of the outcome of this determination within 90 business days from the date of Reclamation's receipt of the feasibility study;
(b) If the feasibility study does not include the required information, you will be notified in writing of the reasons why, and you will have an opportunity to make changes and re-submit the corrected feasibility study to Reclamation for additional review. Where appropriate, Reclamation will work with you to suggest approaches to correct the feasibility study;
(c) Once Reclamation determines that the feasibility study includes all of the required information, Reclamation will review the study to determine, based on application of the criteria set forth in § 404.49, whether or not it is appropriate to recommend to Congress that it authorize construction of the project;
(d) Reclamation's review of the feasibility study will take no longer than 180 business days from the date that Reclamation determines that the study includes all of the required information and is ready for review; and
(e) Reclamation will document its findings in a feasibility report, as more fully described in section § 404.50.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.