§ 418.34 Valid headgate deliveries.

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 418.34, § 418.34 Valid headgate deliveries, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/210358
Permanent ID
ys:prov:210358@1
SHA-256
8208ca0aa44cad2bb64c35f325a9f4a0b468739c1ba20c33ee5970629f926058

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Project water may be delivered to headgates only as provided in §§ 418.8 and 418.10. Water delivered to lands that are not entitled to be irrigated or not in accord with decreed water duties is difficult to quantify at best because it is not typically measured. Since it is not likely to be a part of the total actual headgate deliveries, yet is a part of the total deliveries to the Project, it will manifest itself directly as a lower efficiency. Thus, it will either reduce the District's incentive credit or increase the storage debit by the amount improperly diverted. All other users outside the Project are thereby held harmless but the District incurs the consequence. This approach should eliminate any potential disputes between the District and the Bureau regarding the quantity of water misappropriated.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.