Nev. Rev. Stat. § 338.555
Amounts withheld as retainage; payment of interest
Nevada · Nevada Revised Statutes Chapter 338 — Public Works · Status: effective
Cite this
- Citation
- Nev. Rev. Stat. § 338.555, Amounts withheld as retainage; payment of interest, Nevada, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2104108
- Permanent ID
ys:prov:2104108@1- SHA-256
b7e3c75fa697ed93955207e0c1ab61f682d5bbc0301e94bd349eadc440f1814a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
1. If a public body and a contractor enter into a contract for a public work, the contractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract.
2. After 50 percent of the work required by the contract has been performed, the contractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the contractor, satisfactory progress is being made in the work under the subcontract, and the payment must be equal to that paid by the public body to the contractor for the work performed by the subcontractor. If the contractor continues to withhold retainage from remaining progress payments:
(a) If the contractor does not withhold any amount pursuant to NRS 338.560:
(1) The contractor may not withhold more than 2.5 percent of the amount of any progress payment; and
(2) Before withholding any amount pursuant to subparagraph (1), the contractor must pay to the subcontractor 50 percent of the amount of any retainage that was withheld from progress payments pursuant to subsection 1; or
(b) If the contractor withholds any amount pursuant to NRS 338.560:
(1) The contractor may not withhold more than 5 percent of the amount of any progress payment; and
(2) The contractor may continue to retain the amount of any retainage that was withheld from progress payments pursuant to subsection 1.
3. If the contractor receives a payment of interest earned on the retainage or an amount withheld from a progress payment, the contractor shall, within 10 days after he or she receives the money, pay to each subcontractor or supplier that portion of the interest received from the public body which is attributable to the retainage or amount withheld from a progress payment by the contractor to the subcontractor or supplier.
4. If, pursuant to subsection 3 of NRS 338.515, the public body pays to the contractor an amount of any retainage that was withheld from progress payments pursuant to subsection 1 of NRS 338.515 for the portion of the work which has been performed by the subcontractor, the contractor must pay to the subcontractor the portion of any retainage withheld by the contractor pursuant to this section for the portion of the work.