43 CFR 2569.410
§ 2569.410 What will the BLM do if it finds an error in my application?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 2569.410, § 2569.410 What will the BLM do if it finds an error in my application?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/211125
- Permanent ID
ys:prov:211125@1- SHA-256
393efc6e7c920190bae8460078130c3cb8d4a15295deb4db69e266a8e0bc8fb1
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) If an error is found, the BLM will send you a notice identifying any correctable errors or omissions and whether the error is substantive or technical.
(1) You will have 60 days from the date you received the notice to correct the errors or provide the omitted materials.
(2) If you do not submit the corrections to the BLM within the 60-day period, the BLM will issue a decision rejecting your application and require you to submit a new application.
(b) If the error is a substantive error, your application will not be deemed received until the corrections are made.
(c) If the error is a technical error, your application will be deemed received as of the receipt date. However, the application may still be rejected if the BLM does not receive the corrections within 60 days from the date you received the notice to correct the errors.
(d) If you have uncorrectable defect, then the BLM will issue a decision rejecting your application.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.