43 CFR 2804.40
§ 2804.40 Alternative requirements.
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 2804.40, § 2804.40 Alternative requirements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/211403
- Permanent ID
ys:prov:211403@1- SHA-256
ab6bcb203025e563bdfb3436e5b4a6cd70b60c58ee32580a1d2ac64a3323dcea
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
If you are unable to meet any of the application requirements in this subpart, you may request approval for an alternative requirement from the BLM. Any such request is not approved until you receive BLM approval in writing. Your request to the BLM must:
(a) Show good cause for your inability to meet a requirement;
(b) Suggest an alternative requirement and explain why that requirement is appropriate; and
(c) Be received in writing by the BLM in a timely manner, before the deadline to meet a particular requirement has passed.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.