yourstate.us
43 CFR 2806.70

§ 2806.70 How will the BLM determine the payment for a grant or lease when the linear, communication use, solar energy, or wind energy payment schedules do not apply?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 2806.70, § 2806.70 How will the BLM determine the payment for a grant or lease when the linear, communication use, solar energy, or wind energy payment schedules do not apply?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/211437
Permanent ID
ys:prov:211437@1
SHA-256
03df4b2f9d07ff4cc803e1d9b4e5eb9c8215215ef9a3d3ae187a06b49c34c670

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

When we determine that the linear, communication use, solar, or wind energy payment schedules do not apply, we may determine your payment through a process based on comparable commercial practices, appraisals, competitive bids, or other reasonable methods. We will notify you in writing of the payment determination. If you disagree with the payment determination, you may appeal our final determination under § 2801.10.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.