43 CFR 3101.12
§ 3101.12 Surface use rights.
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3101.12, § 3101.12 Surface use rights, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/211763
- Permanent ID
ys:prov:211763@1- SHA-256
8d8ca106e76fef8de71848794be923043d8742bdc838786d8f2554588d9eb15a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
A lessee will have the right to use only so much of the leased lands as is necessary to explore for, drill for, mine, extract, remove and dispose of all the leased resource in a leasehold subject to applicable requirements, including stipulations attached to the lease, restrictions deriving from nondiscretionary statutes, and such reasonable measures as may be required and detailed by the authorized officer to mitigate adverse impacts to other resource values, land uses or users, federally recognized Tribes, and underserved communities. Such reasonable measures may include, but are not limited to, relocation or modification to siting or design of facilities, timing of operations, specification of interim and final reclamation measures, and specification of rates of development and production in the public interest. At a minimum, modifications that are consistent with lease rights include, but are not limited to, requiring relocation of proposed operations by up to 800 meters and prohibiting new surface disturbing operations for a period of up to 90 days in any lease year.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.