yourstate.us
43 CFR 3137.40

§ 3137.40 What initial development obligations must I define in a unit agreement?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 3137.40, § 3137.40 What initial development obligations must I define in a unit agreement?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/211964
Permanent ID
ys:prov:211964@1
SHA-256
7e817255d3699b810b0ab6c4a65f91440c1a80d2dcbd763bfa5686ee8ec25322

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Your unit agreement must define— (a) The number of wells you anticipate will be necessary to assess the reservoir adequately; (b) A primary target for each well; (c) A schedule for starting and completing drilling operations for each well; and (d) The time between starting operations on a well to the start of operations on the next well.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.