43 CFR 3162.2-6
§ 3162.2-6 When will I have constructive notice that drainage may be occurring?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3162.2-6, § 3162.2-6 When will I have constructive notice that drainage may be occurring?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/212106
- Permanent ID
ys:prov:212106@1- SHA-256
a76046f5a4eee0fffb20aec0319e8212ea83f91023726d403ac848a9b716bf4f
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) You have constructive notice that drainage may be occurring when well completion or first production reports for the draining well are filed with either BLM, State oil and gas commissions, or regulatory agencies and are publicly available.
(b) If you operate or own any interest in the draining well or lease, you have constructive notice that drainage may be occurring when you complete drill stem, production, pressure analysis, or flow tests of the well.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.