yourstate.us
43 CFR 3192.16

§ 3192.16 How will I know if BLM intends to terminate my agreement?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 3192.16, § 3192.16 How will I know if BLM intends to terminate my agreement?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/212449
Permanent ID
ys:prov:212449@1
SHA-256
b8e203e675d3cff0265d36cebf124562b47b37ef9a0bc61d2fa22f9f93b66956

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) If BLM intends to terminate your agreement because you did not carry out the terms of the agreement, BLM must send you a notice that lists the reason(s) why BLM intends to terminate the agreement. (b) Within 30 days after receiving the notice, you must send BLM a plan to correct the problem(s) BLM listed in the notice. BLM has 30 days to approve or disapprove the plan, in writing. (c) If BLM approves the plan, you have 30 days after you receive notice of the approval to correct the problem(s). (d) If you have not corrected the problem within 30 days, BLM will send you a second written termination notice that will give you another opportunity to correct the problem. (e) If the problem is not corrected within 60 days after you receive the second notice, BLM will terminate the agreement.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.