43 CFR 3264.11
§ 3264.11 What must I submit to BLM after I finish subsequent well operations?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3264.11, § 3264.11 What must I submit to BLM after I finish subsequent well operations?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/212669
- Permanent ID
ys:prov:212669@1- SHA-256
594be4330944fa58b440fae1213d0d78ef3d0de9f46f0f1003d04fb0be1cd34a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Submit to BLM a subsequent well operations report within 30 days after completing operations. At a minimum, this report must include:
(1) A complete, chronological history of the work done;
(2) A copy of all logs;
(3) Copies of all directional surveys;
(4) The results of all sampling, tests, or surveys we require you to make (see § 3262.14);
(4) Copies of all mechanical, flow, reservoir, and other test data; and
(5) A statement of whether you achieved your goals. For example, if the well was acidized to increase production, state whether the production rate increased when you put the well back on line.
(b) We may waive this reporting requirement for work we determine to be routine, such as cleanouts, surveys, or general maintenance. To request a waiver, contact BLM. If you do not receive a waiver, you must submit the report.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.