yourstate.us
43 CFR 3273.10

§ 3273.10 When do I need a site license for a utilization facility?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 3273.10, § 3273.10 When do I need a site license for a utilization facility?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/212702
Permanent ID
ys:prov:212702@1
SHA-256
6a0adb3601d4ab191bd3d689990970ecb23a97bc1106de5e3a1fb714caa294e3

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

You must obtain a site license approved by BLM, unless your facility will be located on lands leased as described in § 3273.11. Do not start building or testing your utilization facility on public lands leased for geothermal resources until BLM has approved both your facility construction permit (see § 3272.14) and your site license. The facility operator must apply for the license.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.