yourstate.us
43 CFR 3284.2

§ 3284.2 What are the principal operational responsibilities of the unit operator?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 3284.2, § 3284.2 What are the principal operational responsibilities of the unit operator?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/212813
Permanent ID
ys:prov:212813@1
SHA-256
e8bcfe0bdc33f5138510010d31590b90047f0f213abaeff02080e3420a0b70e1

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

The unit operator is responsible for: (a) Diligently drilling for and developing in the public interest the geothermal resource occurring in the unit area. Only the unit operator is authorized to conduct: (1) Any phase of drilling authorized under subpart 3260 of this chapter, unless another person is specifically authorized by BLM to conduct drilling (see § 3284.3); (2) Resource development activities such as production and injection; and (3) Delivery of the resource for commercial operation. An entity other than the unit operator, such as a facility operator, may purchase or utilize the resource produced from the unit. (b) Providing written notification to BLM within 30 days after any changes to the commitment status of any lease or tract in the unit area (see §§ 3281.9 and 3284.12); and (c) Insuring that the Federal Government receives all royalties, direct use fees, and rents for activities within the participating area.