§ 3284.4 How are unit agreement terms affected after completion of the initial unit well?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 3284.4, § 3284.4 How are unit agreement terms affected after completion of the initial unit well?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/212815
Permanent ID
ys:prov:212815@1
SHA-256
26f28bf6a8e722a28685e32eff41e8252d91dee4886632c721f639b158f85574

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Upon completion of a unit well that BLM determines will produce or utilize geothermal resources in commercial quantities, the unit operator must submit a proposed participating area application under § 3282.3, and no additional drilling to meet unit obligations is required. If no additional drilling in the unit occurs, the unit area will contract to the participating area as specified in the unit agreement. (b) If a unit operator drills a well designed to produce or utilize geothermal resources in commercial quantities, but the well will not produce commercially or is not producible, the unit operator must continue drilling additional wells within the timeframes specified in the unit agreement until a unit well is completed that BLM determines will produce or utilize geothermal resources in commercial quantities. BLM may terminate a unit if additional wells are not drilled within the timeframes specified in the unit agreement. (c) The unit agreement will expire if no well that BLM determines will produce or utilize geothermal resources in commercial quantities is completed within the timeframes specified in the unit agreement. (d) BLM will send the unit operator a written decision confirming that the unit agreement has been terminated or has expired.