Nev. Rev. Stat. § 534.280
Project for recharge, storage and recovery of water: Annual report to State Engineer
Nevada · Nevada Revised Statutes Chapter 534 — Underground Water and Wells · Status: effective
Cite this
- Citation
- Nev. Rev. Stat. § 534.280, Project for recharge, storage and recovery of water: Annual report to State Engineer, Nevada, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2128231
- Permanent ID
ys:prov:2128231@1- SHA-256
059c1973778d9a430c031bff51dd5bfea06350658055b449387eaa40ebe0cae3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
1. Any person who holds a permit for a project must compile and file with the State Engineer annual reports which define the operation of the project and provide such information as the State Engineer requires.
2. Each report must contain either a sworn statement or a certification, under penalty of perjury, that the information contained in the report is true and correct according to the best belief and knowledge of the person filing the report.
3. The annual report must be maintained on a calendar-year basis for the preceding calendar year. If a person who is required to file an annual report under this section fails to file a report when due, the State Engineer may assess and collect a penalty of $500 for each month or portion of a month that the annual report is delinquent. The total penalty assessed under this subsection must not exceed $5,000.
4. The records and reports required to be kept and filed pursuant to this section must be in such form as the State Engineer prescribes.