Nev. Rev. Stat. § 618.835

Disciplinary action; owner of building not liable for employment of another contractor after revocation of license of original contractor

Nevada · Nevada Revised Statutes Chapter 618 — Occupational Safety and Health · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Nev. Rev. Stat. § 618.835, Disciplinary action; owner of building not liable for employment of another contractor after revocation of license of original contractor, Nevada, version 1 as recorded 2026-10-03, yourstate.us, https://yourstate.us/provision/2136458
Permanent ID
ys:prov:2136458@1
SHA-256
dd3ccaaf0ed6c3dbba04d4f43df83ddc8e4dd4090e5e4d12af05c0979c063d1f

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

1. If the Division finds that a person, other than a worker, has violated any of the provisions of NRS 618.780, 618.790, 618.820 or 618.825, or the standards or regulations adopted pursuant to NRS 618.750 to 618.850, inclusive, it may: (a) Upon the first violation, impose upon the person an administrative fine of not more than $15,000. (b) Upon the second and subsequent violations: (1) Impose upon the person an administrative fine of not more than $25,000; and (2) If the person is licensed pursuant to NRS 618.795, revoke his or her license and require the person to fulfill certain training or educational requirements to have the license reinstated. Ê Any penalty imposed pursuant to this section does not relieve the person from criminal prosecution for engaging in the control of asbestos without a license, nor from the imposition of a penalty pursuant to NRS 445B.640. 2. If the license of a contractor for projects for the control of asbestos is revoked pursuant to this section and the owner of a building or structure upon which the contractor is engaged in a project employs another licensed contractor to complete the project, the original contractor may not bring an action against the owner of the building or structure for breach of contract or damages based on the employment of another contractor.