43 CFR 3809.312
§ 3809.312 When may I begin operations after filing a complete notice?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3809.312, § 3809.312 When may I begin operations after filing a complete notice?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/213722
- Permanent ID
ys:prov:213722@1- SHA-256
82105010098a65c5bdcddafcbb91744c408261c6801a1f557fc82d10e64e2cf3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) If BLM does not take any of the actions described in § 3908.313, you may begin operations no sooner than 15 calendar days after the appropriate BLM office receives your complete notice. BLM may send you an acknowledgement that indicates the date we received your notice. If you don't receive an acknowledgement or have any doubt about the date we received your notice, contact the office to which you sent the notice. This subpart does not require BLM to approve your notice or inform you that your notice is complete.
(b) If BLM completes our review sooner than 15 calendar days after receiving your complete notice, we may notify you that you may begin operations.
(c) You must provide to BLM a financial guarantee that meets the requirements of this subpart before beginning operations.
(d) Your operations may be subject to BLM approval under part 3710, subpart 3715, of this title relating to use or occupancy of unpatented mining claims.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.