§ 3809.412 When may I operate under a plan of operations?

United States · 43 CFR — Public Lands: Interior · Status: effective

Get this as JSONEmbed this
Cite this
Citation
43 CFR 3809.412, § 3809.412 When may I operate under a plan of operations?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/213735
Permanent ID
ys:prov:213735@1
SHA-256
7b9da9ab8d6e282c9e20a362ad2a56d473ba4308d6e47460b413aac4e30b836d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

You must not begin operations until BLM approves your plan of operations and you provide the financial guarantee required under § 3809.551.