43 CFR 3809.431
§ 3809.431 When must I modify my plan of operations?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3809.431, § 3809.431 When must I modify my plan of operations?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/213742
- Permanent ID
ys:prov:213742@1- SHA-256
623edf362706d48eaa632f89786da5683a465a004148864aef03b4b7354654c3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
You must modify your plan of operations when any of the following apply:
(a) Before making any changes to the operations described in your approved plan of operations;
(b) When BLM requires you to do so to prevent unnecessary or undue degradation; and
(c) Before final closure, to address impacts from unanticipated events or conditions or newly discovered circumstances or information, including the following:
(1) Development of acid or toxic drainage;
(2) Loss of surface springs or water supplies;
(3) The need for long-term water treatment and site maintenance;
(4) Repair of reclamation failures;
(5) Plans for assuring the adequacy of containment structures and the integrity of closed waste units;
(6) Providing for post-closure management; and (7) Eliminating hazards to public safety.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.