§ 3809.590 When will BLM release or reduce the financial guarantee for my notice or plan of operations?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3809.590, § 3809.590 When will BLM release or reduce the financial guarantee for my notice or plan of operations?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/213764
- Permanent ID
ys:prov:213764@1- SHA-256
a3afc0969f916f1c617b773de4299a72851bdebc579d435aa043c99233997f08
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) When you (the mining claimant or operator) have completed all or any portion of the reclamation of your operations in accordance with your notice or approved plan of operations, you may notify BLM that the reclamation has occurred and request a reduction in the financial guarantee or BLM approval of the adequacy of the reclamation, or both.
(b) BLM will then promptly inspect the reclaimed area. We encourage you to accompany the BLM inspector.
(c) For your plan of operations, BLM will either post in the local BLM office or publish notice of final financial guarantee release in a local newspaper of general circulation and accept comments for 30 calendar days. Subsequently, BLM will notify you, in writing, whether you may reduce the financial guarantee under § 3809.591, or the reclamation is acceptable, or both.