43 CFR 3836.27
§ 3836.27 When must I complete my deferred assessment work?
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3836.27, § 3836.27 When must I complete my deferred assessment work?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/213973
- Permanent ID
ys:prov:213973@1- SHA-256
b750ad56f59b7e7284a7d478045903fcd4e76e895b03df9bb280890d42132a2b
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) You may begin the deferred assessment work any time after the deferment ends. However, you must complete it before the end of the following assessment year. For example, if your deferment ends on July 15, 2008, you must complete all the deferred assessment work by September 1, 2009, in addition to completing the regular assessment work due on that date.
(b) You may also choose to pay the annual maintenance fees for the years deferred instead of performing the deferred assessment work.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.