43 CFR 3860.1
§ 3860.1 Fees.
United States · 43 CFR — Public Lands: Interior · Status: effective
Cite this
- Citation
- 43 CFR 3860.1, § 3860.1 Fees, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/214005
- Permanent ID
ys:prov:214005@1- SHA-256
9c6238c08a3b1b19dc36a582a0aaf92f722a06cbdf0fab06f3b5d2f091efcb26
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Each mineral patent application must include the processing fee found in the fee schedule in § 3000.12 of this chapter to cover BLM's adjudication costs for the application.
(b) As provided at § 3800.5 of this chapter, BLM will charge a separate processing fee on a case-by-case basis as described in § 3000.11 of this chapter to cover its costs for conducting and preparing the validity examination and report.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.