44 CFR 80.21
§ 80.21 Closeout requirements.
United States · 44 CFR — Emergency Management and Assistance · Status: effective
Cite this
- Citation
- 44 CFR 80.21, § 80.21 Closeout requirements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/215375
- Permanent ID
ys:prov:215375@1- SHA-256
1a384f644e20145349a6f10e4c21e1b909fc2b8f643b528f27a0805c7573447b
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Upon closeout of the grant, the subrecipient, through the recipient, must provide FEMA, with the following:
(a) A copy of the deed recorded for each property, demonstrating that each property approved in the original application was mitigated and that the deed restrictions recorded are consistent with the FEMA model deed restriction language to meet the requirements of this part;
(b) A photo of each property site after project completion;
(c) The latitude-longitude coordinates of each property site;
(d) Identification of each property as a repetitive loss structure, if applicable; and
(e) Other information as determined by the Administrator.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.