§ 333.21 Requests for priority rating authority.

United States · 44 CFR — Emergency Management and Assistance · Status: effective

Get this as JSONEmbed this
Cite this
Citation
44 CFR 333.21, § 333.21 Requests for priority rating authority, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/215859
Permanent ID
ys:prov:215859@1
SHA-256
552c9fbab030222f43e53d8bf3f22591e9b3195a9b18e38a2227ba32fafcb814

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) If a rated order is likely to be delayed because a person is unable to obtain items not normally rated under this part, the person may request the authority to use a priority rating in ordering the needed items. (b) Rating authority for production or construction equipment. (1) A request for priority rating authority for production or construction equipment, if needed, must be submitted to the U.S. Department of Commerce on Form BIS-999. (2) When the use of a priority rating is authorized for the procurement of production or construction equipment, a rated order may be used either to purchase or to lease such equipment. However, in the latter case, the equipment may be leased only from a person engaged in the business of leasing such equipment or from a person willing to lease rather than sell. (c) Rating authority in advance of a rated prime contract. (1) In certain cases, and upon specific request, FEMA, in order to promote the national defense, may authorize a person to place a priority rating on an order to a supplier in advance of the issuance of a rated prime contract. In these instances, the person requesting advance rating authority must obtain sponsorship of the request from FEMA or the appropriate Delegate Agency. The person shall also assume any business risk associated with the placing of rated orders if these orders have to be cancelled in the event the rated prime contract is not issued. (2) The person must state the following in the request: “It is understood that the authorization of a priority rating in advance of our receiving a rated prime contract from FEMA (or a Delegate Agency) and our use of that priority rating with our suppliers in no way commits the Delegate Agency, FEMA, or any other Federal Government agency to enter into a contract or order or to expend funds. Further, we understand that the Federal Government shall not be liable for any cancellation charges, termination costs, or other damages that may accrue if a rated prime contract is not eventually placed and, as a result, we must subsequently cancel orders placed with the use of the priority rating authorized as a result of this request.” (3) In reviewing requests for rating authority in advance of a rated prime contract, FEMA will consider, among other things, the following criteria: (i) The probability that the prime contract will be awarded; (ii) The impact of the resulting rated orders on suppliers and on other authorized programs; (iii) Whether the contractor is the sole source; (iv) Whether the item being produced has a long lead time; and (v) The time period for which the rating is being requested. (4) FEMA may require periodic reports on the use of the rating authority granted under paragraph (c) of this section. (5) If a rated prime contract is not issued, the person must promptly notify all suppliers who have received rated orders pursuant to the advance rating authority that the priority rating on those orders is cancelled.